Decision details
Shirehall Redevelopment and Refurbishment Scheme
Decision status: Recommendations Approved (subject to call-in)
Is Key decision?: Yes
Is subject to call in?: Yes
Purpose:
The Portfolio Holder for Corporate Support presented a report from the Director of Place and Enterprise on the proposed redevelopment and refurbishment of the Shirehall, Shrewsbury.
Decision:
RESOLVED:
i.
That in principle agreement to move forward the
option of refurbishing the entire building and progressing the
necessary due diligence and feasibility work to inform the decision
making as outlined in the report be approved.
ii.
That following the completion of further work and
due diligence a report is brought back to Cabinet and then Council
with final recommendations, including final detailed
costings.
iii.
That authority be delegated to the Director of Place
and Enterprise in consultation with the Portfolio Holder for
Corporate Support to progress all works in accordance with
recommendations i) and ii) above.
Publication date: 15/12/2017
Date of decision: 13/12/2017
Decided at meeting: 13/12/2017 - Cabinet
Date comes into force if not called in: 23/12/2017
Call-in deadline date: 22/12/2017