Decision details
Asset Strategy & Corporate Landlord Review Transformation Programme
Decision Maker: Cabinet
Decision status: Recommendations Approved (subject to call-in)
Is Key decision?: Yes
Is subject to call in?: Yes
Decision:
RESOLVED:
That Cabinet:
1. Supported the £3 million approved by the Budget, Transformation and Change Panel for 2026/27 and 2027/28 to fund the Asset Strategy and Corporate Landlord Review Transformation Programme, from the £15 million provision for transformation and change approved by Full Council on 26 February 2026.
2. Supported the new governance arrangements in place since June 2026, set out in Appendix A, including the Asset Transactions Group, chaired by the Section 151 Officer, which oversees two workstreams: (a) the Council’s asset disposal programme; (b) the Asset Strategy and Corporate Landlord Review Transformation Programme.
3. Supported the 2026/27 General Fund asset disposal pipeline of £5,900,120 as at 25 October 2026, comprising £2,637,700 received from completed sales, £1,409,000 from sales agreed but not yet completed, and an indicative £1,853,420 from disposals in preparation or on the market.
4. Supported that £3 million of transformation funding has been approved by the Budget, Transformation and Change Panel for the Asset Strategy and Corporate Landlord Review Transformation Programme across 2026/27 and 2027/28, from the £15 million provision for transformation and change approved by Full Council on 26 February 2026.
5. Agreed that provision of up to £3 million for the Asset Strategy and Corporate Landlord Review Transformation Programme be reflected in the Medium-Term Financial Plan across 2026/27 and 2027/28, with the final profiling of expenditure between financial years determined in accordance with programme requirements and the Council’s financial planning arrangements.
6. Delegated authority to the Section 151 Officer and the Interim Service Director – Place Shaping, in consultation with the Portfolio Holder for Finance, to commission and incur expenditure required to deliver the initial phase of the programme within the approved funding envelope, including the award of commissions and additional staffing resource.
7. Agreed that, following completion of the initial phase, a further report is intended to be submitted to Cabinet in Quarter 1 of 2027/28, informed by relevant milestones and outputs from the Council’s wider transformation programme, setting out:
(a) progress with the Asset Strategy and Corporate Landlord Review Transformation Programme;
(b) the assessment of the Council’s existing arrangements against the requirements of a Corporate Landlord model;
(c) expenditure incurred and the forecast funding requirement for the remainder of the programme;
(d) the early opportunities identified for capital receipts, revenue savings and additional income; and
(e) the proposed scope, delivery approach, anticipated benefits and funding requirement for the principal phase of the programme, together with any further approvals required from Cabinet
Report author: Duncan Whitfield
Publication date: 18/11/2026
Date of decision: 18/11/2026
Decided at meeting: 18/11/2026 - Cabinet
Date comes into force if not called in: 26/11/2026
Call-in deadline date: 25/11/2026
Current call-in Count: 0
Accompanying Documents: