Cambrian Railway Building Oswestry - Request for Capital Funding to Match UKSPF Grant Offer
Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Decision:
RESOLVED:
That Cabinet:
1. Delegated authority to the Executive Director for Resources to enter into an Agreement with the UKSPF to restore the exterior of the building and to secure £630,250 in grant aid.
2. Approved match funding of £270,107 of capital to be financed through borrowing.
3. Provided Authority to Proceed with the project to restore the exterior of the Cambrian Railway Building in Oswestry and requested that the capital programme is updated to reflect Cabinet approval of this report, within the capital programme being approved by Council on 29 February 2024.
4. Delegated authority to the Executive Director for Place to proceed with the delivery of the exterior restoration including listed building consent, detailed design, tendering of works and construction.
5. Once the Conservation Management Plan and surveys are complete a business case for the re-use of the Cambrian Building is brought back to the Cabinet for review and consideration of any additional investment required to restore the interior of the building and make it suitable for re-use.
Report author: Steve Law
Publication date: 17/01/2024
Date of decision: 17/01/2024
Decided at meeting: 17/01/2024 - Cabinet
Effective from: 25/01/2024