Decision details
Shrewsbury Town Centre Redevelopment Programme: Phase One
Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Decision:
RESOLVED:
3.1. That Cabinet:
3.1.1. Approved the submission of a planning application for the demolition of the Riverside shopping centre and the former Riverside medical practice, and enabling work, construction of the proposed park and temporary greenspace (as set out in the Council report 6 July 2023), all aligned to the Levelling Up Fund bid award for the Smithfield Riverside Redevelopment Programme (Project 1) of £14.85m.
3.1.2. Agreed to commencement of the stakeholder engagement and public consultation programme on the emerging masterplan for Smithfield Riverside.
3.2. Delegated responsibility to the Executive Director of Place, in consultation with the Section 151 Officer and the Portfolio Holders for Climate Change, Environment and Transport, Economic Growth and Regeneration and Housing and Assets, to progress the capital project (item 3.2.1 above), to include, but not limited to, the following:
3.2.1. Finalise the masterplan for the wider Smithfield Riverside redevelopment area following the outcomes of the stakeholder engagement and public consultation programme, as provided for in Recommendation 3.1.2 above, and for inclusion in a further report for final approval by Council.
3.2.2. Finalise planning strategy for future phases of development for the Shrewsbury Town Centre Redevelopment Programme: Smithfield Riverside Phase One, following the outcomes of the stakeholder engagement and public consultation programme, as provided for in Recommendation 3.1.2 above, and for inclusion in a further report for final approval by Council
3.2.3. Undertake an options and feasibility study for the retention, reconstruction and/or replacement of Ravens Meadow multi-storey car park, necessary to inform future phases of the Smithfield Riverside masterplan, and for inclusion in a further report for final approval by Cabinet and Council.
3.3. That Cabinet agreed to recommend to Council to:
3.3.1. Progress the above works as a capital project to completion of contract documentation and receipt of tenders, for demolition, enabling works and construction of the park and associated temporary greenspace within the Levelling Up Fund bid award for the Smithfield Riverside Redevelopment Programme (Project 1) of £14.85m.
Report author: Tim Pritchard
Publication date: 18/10/2023
Date of decision: 18/10/2023
Decided at meeting: 18/10/2023 - Cabinet
Effective from: 26/10/2023
Accompanying Documents: