Capital Monitor 2016/17 Quarter 1
29/07/2016 - Capital Monitor 2016/17 Quarter 1
RESOLVED:
i) That net budget variations of £4.4m to the 2016/17 capital programme, detailed in Appendix 1/Table 1 and the re-profiled 2015/16 capital budget of £66m be approved. Including new allocations of capital receipt funding as follows:
§ £0.036m for works to a shop unit at Shoplatch.
ii) That the re-profiled capital budgets of £43.1m for 2017/18 and £18.8m for 2018/19 and £1.8m for 2019/20 as detailed in Appendix 1/Table 4 be approved.
iii) That the expenditure to date of £5.7m, representing 9% of the revised capital budget for 2016/17, with 25% of the year having elapsed, be accepted.