Capital Monitor 2014/15 Period 5
15/10/2014 - Capital Monitoring Report Quarter 2 2014/15
(a) That approval be given to net budget variations of £1.3m to the 2014/15 capital programme, detailed in Appendix 1/Table 1 and the re-profiled 2014/15 capital budget of £69.6m. Including new allocations of capital receipt funding as follows:
· The Tannery Building Refurbishment Shrewsbury Hub £511,000;
· Smallholding Refurbishment £149,940; and
· Theatre Severn – Digital Projector £38,500.
(b) That approval be given to the re-profiled capital budgets of £22.3m for 2015/16 and £5.3m for 2016/17 as detailed in Appendix 1/Table 4.
(c) That the expenditure to date of £14.9m, representing 21.4% of the revised capital budget for 2014/15, with 42% of the year having elapsed, be accepted.