Issue - decisions
Capital Monitor Quarter 2 2015/2016
16/10/2015 - Capital Monitoring Report Quarter 2 2015/2016
RESOLVED:
i) That the net budget variations of £3m to the 2015/16 capital programme be approved, detailed in Appendix 1/Table 1 and the re-profiled 2015/16 capital budget of £62m. Including new allocations of capital receipt funding as follows:
§ £86k for the Mere warden’s bungalow refurbishment.
ii) That the re-profiled capital budgets of £40.9m for 2016/17 and £28.1m for 2017/18 and £70k for 2018/19 be approved as detailed in Appendix 1/Table 4.
iii) That the expenditure to date of £14.4m be accepted, representing 23.2% of the revised capital budget for 2015/16, with 42% of the year having elapsed.