Shropshire Council

Town centre improvements

Once the key junction improvements are completed, a programme of enhancement works in Shrewsbury town centre will be carried out.

This work is set to begin early in 2018 and be completed by autumn 2019. 

Improvements in the town centre will incorporate a range of traffic management and public realm enhancements as a part of the overall SITP.

The locations of the improvements include:

  • Town Centre Gateway at English Bridge / Abbey Foregate;
  • “Light touch” enhancement of existing spaces at The Square;
  • “High Street Style” improvements at Mardol and Roushill;
  • Junction improvements at Dogpole, Town Walls / Belmont, Murivance / Swan Hill, Murivance / St. John’s Hill, Murivance / Quarry and Mardol / Smithfield Road;
  • Junction improvements at Bellstone / Shoplatch and Mardol / Roushill;
  • College Zone at Claremont Bank; and
  • Pride Hill Enhancement - find out more from the work plan.

Wyle Cop and English Bridge enhancements - January to March 2018

Work is due to start on Monday 8 January 2018 to upgrade the footways – and resurface the road – between Wyle Cop and English Bridge in Shrewsbury.

The work is due to last approximately nine weeks, and road users are being alerted to some road closures while the work is carried out.

This work is being carried out as part of the Shrewsbury Integrated Transport Package (SITP) and will include the upgrading of footway and kerbing materials with natural stone products, plus carriageway resurfacing. The aim is to enhance and improve the area and complete the new Abbey Foregate ‘gateway’ to the town centre.

Footway re-paving and kerbing

The footway re-paving will be done in two phases. The southern footway (the Lion & Pheasant side) will be carried out in phase 1. The northern section (on the NCP car park side of the road) will be carried out in phase 2.

While the footway re-paving and kerbing work is carried out, the footways will be closed and temporary walkways will be provided for pedestrians. Access will be maintained to businesses and residential properties.

Meanwhile, Wyle Cop will be closed to traffic in a downhill direction (heading out of town) for the duration of the footway and kerbing work, and a signed diversion route will be in place.

Carriageway resurfacing

The resurfacing work will take place overnight, between 8pm and 6am, for five nights – starting on Monday 26 February. During these times Wyle Cop will be closed in both directions and Beeches Lane (Town Walls) will also be closed.

The St Julian’s Crescent one-way system will be reversed, with traffic exiting via Beeches Lane. Access into St Julian’s Crescent will be via English Bridge, and all vehicles will need to wait to be escorted through the closure. A drawing of the proposed footway and carriageway work give more detail.

Take a look at the one way closure diversion route and full closure diversion route

Pride Hill upgrade – 30 April to November 2018, and February to spring 2019 

Work will include:

  • Resurfacing the pedestrianised area with high-quality materials to reinforce the character of the street;
  • Replacing existing street furniture to reflect the proposed high quality finish;
  • Reducing street clutter;
  • Improving pedestrian connections at either end of the street;
  • Emphasising key access points with the street with the use of informal banding;
  • Enhancing the setting of High Cross; and
  • Retaining the existing trees.

Access to properties will be maintained at all times, with temporary pedestrian walkways being implemented where required. The contractor will have pedestrian ambassadors and a public liaison officer on-site to assist with enquiries and access arrangements for deliveries during the construction works.

View the plan of works for Pride Hill

Update: December 2018

Work to upgrade and enhance Pride Hill will re-start early next year, following the Christmas and new year break. The work is planned to begin again on 4 February 2019, with an anticipated completion date of spring 2019.

Unfortunately, the delivery of the scheme this year was not what Shropshire Council expected and, as a result, the council will not be proceeding with the previous contractor. However, we’re pleased to announce the appointment of a new contractor, McPhillips (Wellington) Ltd. Their locality and previous experience will allow the successful delivery and completion of the works, to the required and expected standard.

We’ll soon be recommencing our formal consultation with Shrewsbury BID, Shrewsbury Town Council, other key stakeholders and businesses, in order to successfully complete the scheme with the least amount of disruption possible.

Update: January 2019

Letter to businesses/residents affected by recommencing work on Pride Hill upgrade and enhancement project.

Castle Street and St Mary’s Street resurfacing – August 2018

Castle Street and St Mary’s Street in Shrewsbury will be closed overnight (from 8pm to 6am) from Tuesday 14 August 2018 for resurfacing work. It’s estimated that the works will take three nights to complete. The work is being carried out as part of the Shrewsbury Integrated Transport Package (SITP).

While work is carried out the road will be closed from Castle Gates at the junction with Smithfield Road, with a signed diversion route in place.

During the road closure access will be maintained to residents and businesses only. An access route will be provided via Windsor Place, with the one-way being reversed.

The work is weather dependent and may be subject to unforeseen delay and date changes.

As usual with works of this nature there will be disruption whilst the works are undertaken, but every effort will be made to keep any disruption and noise to a minimum. We thank people for their understanding.

Town Walls to Claremont Bank improvements

The above scheme will commence on 10 September 2018, and be carried out in three separate phases. The first phase - Murivance and adjoining roads – will end in November 2018.

Work will recommence concurrently in early January on phase 2 - Claremont Bank, and phase 3 - Town Walls - with completion anticipated in spring 2019.

The work will include: the upgrading of footway materials to improve the aesthetic appearance of the area; improvements to footway crossing facilities along the whole route; and improved road layout and parking. Each of the phases will include carriageway resurfacing.

During the work there will be several traffic management phases implemented, in order to accommodate the safe construction of these works for the travelling public, and the contractors’ workforce. The road will remain open for the main part of the works with lane closures and temporary traffic signals in operation. The carriageway resurfacing works will be undertaken under a full closure at the end of each phase.

You can view the traffic management plan for Murivance here, and more information will be provided on variable messaging signage throughout the period of the works.

It should be noted that this work is weather dependent and part of a larger overall programme which may be subject to unforeseen delays.

As usual with works of this nature there will be some disruption whilst the works are undertaken, however every effort will be made to keep any disruption to a minimum. We thank people for their understanding while this important work is carried out.

Take a look at the general arrangement drawings for more information:

Murivance and Town Walls in Shrewsbury (including Kingsland Bridge, Swan Hill, Quarry Place and St John’s Hill) will be closed for resurfacing from Monday 29 October for approximately one week, as part of town centre improvement works being carried out under the Shrewsbury Integrated Transport Package (SITP).

During this time the road will be closed to vehicles with access maintained to residents and local businesses only. No through traffic will be permitted and signed diversion routes (route 1 and route 2) will be provided where necessary. Traffic management personnel will be posted at each closure point to assist with access.

As the work is weather dependent and part of a larger overall programme, it may be subject to unforeseen delays.

Every effort will be made to keep any disruption to a minimum and we thank people for their understanding while this important work is carried out.

Town Walls to Claremont Bank - phases 2 and 3

Claremont Bank (Murivance to Lower Claremont Bank)Works will commence on Monday 7 January until April 2018

Town Walls (Belmont junctions) Works will commence on Monday 21 January until April 2018

The work will include:

  • the upgrading of footway materials to improve the aesthetic appearance of the area;
  • improvements to footway crossing facilities along the whole route;
  • improved road layout and parking.
  • Each of the phases will include carriageway resurfacing.

During the work there will be several traffic management phases implemented in order to accommodate the safe construction of these works for the travelling public, and the contractors’ workforce. The road will remain open for the main part of the works with lane closures and temporary traffic signals in operation. More information will be provided on variable messaging signage throughout the period of the works.

The carriageway resurfacing works will be undertaken under a full daytime closure at the end of each phase, with diversion routes in place.

Scheme drawings are available in the related documents section of this page.

Town Walls to Claremont Bank update - 14 March 2019

As part of the work there will be several short term closures between Beeches Lane (Town Walls) and Lower Claremont Bank of approximately one week each, to allow the safe construction and completion of improvement works in narrow areas.

The first closure will be from Monday 18 March until Wednesday 27 March [2019], to allow work to be carried out at the Town Walls/Belmont junction.

During this closure Town Walls access will be maintained for residents and businesses only, up to the cathedral, with the exit being out via Town Walls and Williams Way. No through traffic will be permitted after the cathedral and diversion routes will be signed for all other through traffic.

The second closure – to allow work to be carried out at Claremont Bank (St Chad’s Terrace) – will be implemented on Monday 15 April for one week. Access will be maintained via local roads for residents and businesses, with signed diversion routes in place for through traffic.

Work being carried out as part of the Town Walls to Claremont Bank improvements includes: the upgrading of footway materials to improve the aesthetic appearance of the area; improvements to footway crossing facilities along the whole route; improved road layout and parking, and carriageway resurfacing.

The following maps illustrate the plans...

Town Walls to Claremont Bank update - 23 April 2019

One of the final stages of the Town Walls to Claremont Bank work is the resurfacing of the road. This work will take place between 22 April and 5 May 2019 and will require the roads to be fully closed to traffic so that work can be carried out safely.

As with previous closures, the road will be closed from Beeches Lane (Town Walls) at its junction with Williams Way, with diversions routes in place. Traffic management operatives will be stationed at each closure point to allow access for residents and businesses only.

In addition, from the week commencing 15 April there will be some short-term closures to allow new streetlighting and kerbing to be installed within narrow areas on Claremont Bank. These closures are only expected to last during daytime working hours.

Once the resurfacing work is complete, the final paving will be completed on the new footpaths, with works anticipated to be fully complete by mid-May 2019.

Work being carried out as part of the Town Walls to Claremont Bank improvements includes: the upgrading of footway materials to improve the aesthetic appearance of the area; improvements to footway crossing facilities along the whole route; improved road layout and parking, and the carriageway resurfacing.

Find out more from the closure plan.