Shropshire Council

2024/25 bridge maintenance programme

Bridge name / description

Bridge number

URS no.

OSGR or postcode

Works description

Planned date of work

Betton Street Railway Footbridge

B5091

F4085/ 10

SJ 499 118

Remove Redundant Structure over Shrewsbury to Hereford Line. Slip in programme to 2024/ 25 due to ongoing correspondence with NR regarding possession dates and delay damage costs.

To be confirmed

Montague Street Railway Footbridge

B5234

F4072/ 10

SJ 497 113

Maintenance of sub-standard bridge elements . Budget Construction Costs to be confirmed. Slip in programme to 2024/ 25 due to ongoing correspondence with NR regarding Possession Dates and delay damage costs.

To be confirmed

Bind Footbridge

B4904

U8148/ 20

SO 726 837

Replace surfacing and parapet walls/ railings washed away in floods during 2021/22.

To be confirmed

(June / July 2024) 

RoW - Adcote Mill Footbridge

B7048

U1716/ 10

SJ 422 195

Replacement of Rights of Way (RoW) footbridge which has partially collapsed. This is subject to conclusion of current Legal Proceedings.

To be confirmed

Rindleford Footbridge

B4901

U7115/ 10

SO 737 955

Removal of collapsed footbridge

To be confirmed

Broad Bridge

B4330

B4176/ 45

SO 761 981

Masonry and pointing works to cutwaters and arches.

To be confirmed

(June / July 2024)

Meole Brace Bridge

B5327

A5191/ 10

SJ 490 107

Concrete repairs to soffit

To be confirmed

(August 2024)

Meole Brace Footbridge

B5328

A5191/ 10

SJ 490 107

Replace surfacing and repaint existing structure.

To be confirmed

(August 2024)

Upper Craignant

B1784

U0109/ 10

SJ 254 350

Culvert Replacement

To be confirmed

Pimley Manor River Severn Bridge

B5136

A49/ 15

SJ 523 140

Undertake maintenance painting to existing structure.

To be confirmed

(August / Sept 2024)

Uffington River Severn Bridge

B3132

A49/ 15

SJ 524 134

Undertake maintenance painting to existing structure.

To be confirmed

(August / Sept 2024)

Nant Lane Retaining Wall

Division 1

U0119/ 15

SO 581 746

Special inspection 2022 identified a collapsed section of retaining wall circa 15 square metres. Retaining wall to be repaired/ rebuilt.

To be confirmed

A490 Chirbury to Churchstoke Embankment Slip

A490/40

A490/40

SY15 6DS
OSGR 327265 296030

Hard engineered piling solution required to fix 25m section of slipped embankment. Temporary/permanent traffic lights installed as temporary measure whilst solution is being completed.

To be confirmed

A488 Hope Valley Embankment Slip.

A488/361

A488/361

SJ350017

Pining solution required to 15m section of slipped embankment. Temporary traffic lights installed as temporary measure whilst solution is being completed.

To be confirmed