2021/22 drainage works programme
This information is correct at the time of publishing but could be subject to change either due to circumstances beyond our control, or should other works come in that make it more efficient and less disruptive to reschedule
Closure details
- Starts: 19 January 2022
- Ends: 20 March 2022
- All Shropshire
Area | Location | Start date | End date |
Northeast | Pear Tree Lane, Whitchurch | 07/03/2022 | 20/03/2022 |
Northeast | Little Soudley Rd, Soudley - Drainage 24hr closure | 19/01/2022 | 28/01/2022 |
Southeast | Astbury Lane, Chelmarsh | 07/02/2022 | 20/02/2022 |
Southeast | Ludlow Rd East Roundabout, Bridgnorth | 21/02/2022 | 06/03/2022 |