2023/24 bridge maintenance programme
Bridge name / description |
Bridge number |
URS no. |
OSGR or postcode |
Works description |
Planned date of work |
Betton Street Railway Footbridge |
B5091 |
F4085/ 10 |
SJ 499 118 |
Remove Redundant Structure over Shrewsbury to Hereford Line. Slip in programme to 2024/ 25 due to ongoing correspondence with NR regarding possession dates and delay damage costs. |
To be confirmed
|
Montague Street Railway Footbridge (B5234) |
B5234 |
F4072/ 10 |
SJ 497 113 |
Maintenance of sub-standard bridge elements . Budget Construction Costs to be confirmed. Slip in programme to 2024/ 25 due to ongoing correspondence with NR regarding Possession Dates and delay damage costs. |
To be confirmed |
Frodesley Lane Culvert next to Brook House |
Divisional Culvert |
C5156/ 21 |
SY5 7QG |
Culvert replacement. |
Completed 26 October 2023 |
A488 Wagbeach Culvert |
Divisional Culvert |
A488/ 375 |
SJ 364 028 |
Repairs to downstream end of culvert which has collapsed. |
Completed 14 July 2023 |
B1416 Mustard Pot Culvert |
B1416 |
C1004/ 16 |
SJ 288 341 |
Culvert replacement. |
|
B3329 Cressage Bridge |
B3329 |
B4380/330 |
SJ 593 045 |
Stabilised collapsing section of embankment on approach to bridge and filling in voids detected under the verges and main deck carriageway. Works include installing a concrete over-slab, waterproofing deck and renewing the deck surfacing. |
Completed 12 March 2024 |
B6728 Five Turnings Bridge |
B6728 |
U6013/ 10 |
SO 365 864 |
Take down and rebuild 2m section of upstream arch and underpin foundations and install concrete aprons to both abutments and install concrete invert to bed of watercourse . |
Completed 25 September 2023 |
Collybrook Park Retaining Wall |
Division 6 |
C6336/ 76 |
SO 581 746 |
Special inspection 2022 identified a collapsed section of retaining wall circa 15 square metres. Retaining wall to be repaired/ rebuilt. |
Completed 18 September 2023 |
Nant Lane Retaining Wall |
Division 1 |
U0119/ 15 |
SJ 267 345 |
Stabilise collapsing retaining wall structure using possible ground anchors ie Platypus or Duck Bill Anchors, with reinforced concrete slab and facing stonework solution. |
To be confirmed |
B4904 Bind Footbridge |
B4904 |
U8148/ 20 |
SO 726 837 |
Replace surfacing and parapet walls/ railings washed away in floods during 2021/22. |
To be confirmed |
B4410 Rea No.2 Bridge |
B4410 |
C4223/ 30 |
SO 618 898 |
Filling is void to downstream right verge and installing a grip drain. |
Completed 25 July 2023 |
B4328 Bridgnorth Bridge |
B4328 |
B4363/220 |
SO 718 930 |
Further trial holes will be required to determine extent of services over the bridge in 2023/24. A major maintenance scheme involving extensive concrete and stone work repairs, re-waterproofing and parapet upstand, parapet and deck surfacing replacement is being designed for commencement in 2024/25 |
To be confirmed |
RoW - Adcote Mill Footbridge |
B7048 |
U1716/ 10 |
SJ 422 195 |
Replacement of Rights of Way (RoW) footbridge which has partially collapsed. This is subject to conclusion of current Legal Proceedings. |
To be confirmed |
A490 - Chirbury to Churchstoke Embankment Slip |
A490/40 |
A490/40 |
SY15 6DS |
Hard engineered piling solution required to fix 25m section of slipped embankment. Likely to be late 2023/ early 2024 before works can commence. Temporary/permanent traffic lights installed December 2021 as temporary measure whilst solution is being worked up. |
To be confirmed |
B5232 Abbey Foregate Bridge |
B5232 |
C7200/11 |
SJ504 122 |
Replace damaged section of steel parapet. |
Completed 23 August 2023 |
B5221 Smithfield Road Cantilevers |
B5221 |
A458/220 |
SJ490 128 |
Drill and fix top hat section to steel rails. Replacement of corroded steel pedestrian gate. Painting works to steel railings. |
Completed 20 November 2023 |
CG45 Doddington Cattle Grid |
CG45 |
A4117/80 |
SO 615 761 |
Cattle grid replacement. Temporary traffic lights installed until cattle grid has been replaced |
Completed 12 March 2024 |