This information is correct at the time of publishing but could be subject to change either due to circumstances beyond our control, or should other works come in that make it more efficient and less disruptive to reschedule
Closure details
- Starts: 23 May 2022
- Ends: 15 June 2022
- Central Shropshire
Severn Trent Water
From junction of Newtown to outside Station Cottage
Replace 529m of existing water main with new 90mm and 180mm PE water main water and Associated fittings by open cut, directional drill and slip line, make connections to existing network and renew service supply pipe to customer properties once the sample results have been confirmed, Remove redundant iron work and make good. Backfill, reinstate and site clear.