Large-scale project works
This page will be kept up to date with large scale project works. You can filter by area and/or status to easily find what you are looking for.
Resurfacing - St Johns Street, Whitchurch
Runs from 31 January 2020 to 31 March 2020 North ShropshireWork as part of a £5m package of highways surface improvements to 26 roads across Shropshire before the end of March 2020. Please note that the dates on this page refer to the package generally and not this work specifically.
Resurfacing - Bank Farm Road, Shrewsbury
Runs from 31 January 2020 to 31 March 2020 Central ShropshireWork as part of a £5m package of highways surface improvements to 26 roads across Shropshire before the end of March 2020. Please note that the dates on this page refer to the package generally and not this work specifically.
Resurfacing - B4555 Chelmarsh
Runs from 31 January 2020 to 31 March 2020 Central ShropshireWork as part of a £5m package of highways surface improvements to 26 roads across Shropshire before the end of March 2020. Please note that the dates on this page refer to the package generally and not this work specifically.
Resurfacing - Shadymoor Lane, Church Pulverbatch
Runs from 31 January 2020 to 31 March 2020 Central ShropshireWork as part of a £5m package of highways surface improvements to 26 roads across Shropshire before the end of March 2020. Please note that the dates on this page refer to the package generally and not this work specifically.
Resurfacing - The Graig, Llanfairwaterdine
Runs from 31 January 2020 to 31 March 2020 South ShropshireWork as part of a £5m package of highways surface improvements to 26 roads across Shropshire before the end of March 2020. Please note that the dates on this page refer to the package generally and not this work specifically.
Resurfacing - Coalport Road, Broseley
Runs from 31 January 2020 to 31 March 2020 Central ShropshireWork as part of a £5m package of highways surface improvements to 26 roads across Shropshire before the end of March 2020. Please note that the dates on this page refer to the package generally and not this work specifically.
Resurfacing - Kerry Lane, Bishop’s Castle
Runs from 31 January 2020 to 31 March 2020 South ShropshireWork as part of a £5m package of highways surface improvements to 26 roads across Shropshire before the end of March 2020. Please note that the dates on this page refer to the package generally and not this work specifically.
Resurfacing - Stanton Road, Shifnal
Runs from 31 January 2020 to 31 March 2020 Central ShropshireWork as part of a £5m package of highways surface improvements to 26 roads across Shropshire before the end of March 2020. Please note that the dates on this page refer to the package generally and not this work specifically.
Resurfacing - A41 Tong
Runs from 31 January 2020 to 31 March 2020 North ShropshireWork as part of a £5m package of highways surface improvements to 26 roads across Shropshire before the end of March 2020. Please note that the dates on this page refer to the package generally and not this work specifically.
Resurfacing - The Evergreens, Sheriffhales
Runs from 31 January 2020 to 31 March 2020 Central ShropshireWork as part of a £5m package of highways surface improvements to 26 roads across Shropshire before the end of March 2020. Please note that the dates on this page refer to the package generally and not this work specifically.